Skip to content
AON CENTER

Case Study

AON Center

Leading the Way in Sustainability and Social Responsibility in the Construction Industry

AON Center: Design & Bid Management for the 27th Floor

JLL’s headquarters building, AON Center, faced a waterproofing membrane issue. The membrane on the 27th floor, which is the floor that intakes all of the building’s air, reached the end of its service life and needed to be replaced. JLL hired RAM Companies (a Synergy Partner) to perform professional roof consulting services.

Customized Solution

Provided RRC consulting services, which included:

  • Detailed Specifications
  • Bid Management
  • Project Administration
  • Project Oversight during construction
  • Customized Specifications based on Surveys and RRC observations
  • There were (5) bidders invited to the RFP, and RAM Companies managed the entire bidding process
  • Bid Management made sure that the proper bidders worked on the job
  • Worked closely with the JLL team to deliver a safe & quality project

Results

  • Tight specifications provided the contractors to bid accurately
  • Received competitive bids from multiple contractors
  • Information from the bids allowed RAM USA and the client to choose the right contractor for the job
  • Proper Bid Management helped the project come in under budget, thus, saving money – bids came in lower due to better specifications and a tighter bidding process by approximately 25%
  • Fast turnaround and delivered ahead of schedule
  • Proper design, product selection and project management prevented fumes from entering the ventilation system, and we worked after hours to minimize interference and fumes
  • The process increased quality and reduced cost
Client

JLL AON Center

Sites Scanned

1

Total Sq. Footage

3200

Project Type

Diagnostic Roof Assessments

Cost Savings

$60,000

Related Projects